DAYS 53, 54, 55
So the last three days were mostly about the roughing out the electric. Along with that, my skylight was installed in the back hallway, the roof over the bathroom/hallway was also shingles...so the entire roof is now 100% done. Also the siding has been underway, with the fascia/soffit work, and hopefully in the next week or so, in-between the holidays, the bulk of the siding will be completed.
Work has also started in my foyer...and I expect the plumber will be back on Monday to start his rough installation. In the mean time, I've ordered all the fixtures for the bathroom...boy, what a PITA trying to pick out faucets and toilets, not to mention the lighting and the peripherals that normally go in a bathroom.
I also started my wiring of the audio power distribution...I still have some more to do (so does the electrician), but now waiting on my contractor to fur out the old wall to a 6" stud wall, since the old wall was only done with 4" studs. Once that's ready (he should be doing that tomorrow) the rest of the power lines will be run.
In the picture, the blue boxes are for my stuff...the black ones are the electrician's power layout. He also hung a bunch of lights, and ran some extra power to the 4 beams that will be exposed...so that at some point I can add some track lighting, or whatever, without having to worry about running lines.
Monday the electric inspector should also be coming to check the rough-in of the power. After the electric is done and the plumbing, the insulation phase is next...which I hope will be NLT the 2nd week of Jan...and then the last 2 weeks should be the drywall.
Of course...there is also some floor work to be done in the foyer and bathroom/hallway...not sure when that will fall into place.
Oh...the day after Xmas, my floor installer should be here for 3-4 days putting in the sub-floor...and Monday the lumber for that should be arriving.
It's been a busy few days for me...I've been working a lot and up late every night getting my shit together for the next day.